Inspection of the drilling site at the end of May. The power plant will be built between the two drilling rigs starting in the fall / photo: Willibald company
The drilling sites have been completed. The drilling site in Gelting still looks empty. Starting next week, the material for drilling site A will be delivered. Then there will be about 130 truckloads of equipment. The central element will be the 60-meter-high drilling rig.
Deliveries will take place from June 5 until around June 20 . The second rig will be delivered around mid-July. During this time, there will be an increased volume of truck traffic.
Eavor apologizes to local residents for any inconvenience.